  • Repair Work
  • Civilian

  • October 24, 2019

  • Athens

  • -

Project information

Due to the rising humidity, the columns on the ground floor of the building were oxidized. Α problem that was addressed with the following interventions:

  • Dismantling of all the weathered parts of concrete and full coverage of the corroded armaments.

  • Cleaning of all the surfaces that have been oxidized.

  • Enforcement of the columns, whenever it was deemed necessary.

  • Coating of the armaments with corrosion inhibitor.

  • Coating with resinous reparative mortar.

  • Application of finely milled finishing mortar for protection, smoothing and finishing.

  • Application of gas-phase corrosion inhibitor on the columns wherever it was deemed necessary.